|
|
The Remington Group Flow Mfg. Article Manufacturing In The New Millennium The Remington Group, LLC 475 Wall Street Princeton, New Jersey 08540 (609) 497-6400
|
|
|
|
|
Last update: 07/26/2002 |
|
|
|
|
|
|
|
|
|
|
|
Article Back to Home Back to Articles Flow
Manufacturing is the Essential Component in Your Supply Chain
Strategy Well, it’s the dawn of the new millennium and the age of the Supply
Chain. We’ve successfully
survived the Y2K non-crisis and, in the process, gotten a new ERP System
to back bone the company’s information management infrastructure. Now we
are entering the new age of Supply Chain Management trying to tie all the
nodes of the supply chain together so that materials flow seamlessly along
a path beginning with a customer’s order and pulling through from the
raw material supplier all the way through the process.
All of this is good. The
previous ten years were turbulent ones for the manufacturing/materials
executive as we absorbed the new disciplines of the period and saw the old
ones disappear: ERP replaced MRP ll, the Just-in-Time wave from the far
east morphed into Demand Based Flow, shop organization went from
functional to product based and, the multitudinous materials management
functions began to creep together into a homogenous unit known as the
Supply Chain. Supply Chain Management is to the twenty first century manufacturing
enterprise as MRP was to the factory of the 1970s; the overriding
framework that points the business toward the customer.
The customer of the MRP and post MRP era could put up with the
fixed (and mostly long) lead times, inflexible product structures and, the
high cost of batch/subassembly/final assembly manufacturing and inventory
management of that time. Not
so the customer of the Supply Chain Management era.
As we begin the Supply Chain Management era with the market’s
demand for flexibility, velocity and, minimal waste (not necessarily no
waste), we now focus on this new overriding framework that is under-girded
by ERP and empowered by modern Flow Manufacturing.
The MRP era had a good run of some twenty years and, as it was
“invented here”, was widely accepted.
The JIT era, not “invented here” and less universally accepted,
had to be culturally attuned to our western culture and became Flow in the
mid nineties. It’s run as
Flow, before the universal move toward Supply Chain Management (invented
here), has only been about five or six years, hardly enough time to gain
wide currency. Hell, flow seminars have dried up and the last one I attended
still had an agenda item on “defining flow.”
Don’t get me wrong, there are lots of successful flow factories
and we really do know what flow manufacturing is and how to do it.
Since manufacturing is at the heart of the supply chain, the
question, in the Supply Chain Management era, is: have we made flow
operations dovetail with our rapidly developing supply chain strategies
and really compliment them? Lets
look at some of the issues involved in doing just that. PRODUCTS AND SUPPLY
CHAINS
Every supply chain is different and the driver of differentiation is the
products or product lines in the particular supply chain.
In fact the same company can have more than one supply chain
depending on the value chain perceived by the customers of a particular
supply chain and it’s products. So
if supply chains exhibit different characteristics depending on their
place in the customers’ value chain, it stands to reason that the heart
of the supply chain, the flow manufacturing operation, should be specific
to the particular supply chain. Taking
a hard look at products and supply chains and categorizing them permits us
to start tailoring the flow operation to each one and thereby make the
individual supply chains more sensitive to the customers’ value chain. “Commodity” products. These
types of products exhibit characteristics of price elasticity and
sensitivity and are usually only differentiated by customer service in the
supply chain. They have
inherently low margins. The supply chain for these products needs to have
all the waste squeezed out of it, be one that moves product through at
high velocity, has short lead times and, is ripe for a low cost producer
strategy. Depending on the
complexity of the product line, demand forecasts for these products should
be reasonably reliable and finished goods inventory can be deployed in
small buffer quantities in limited strategic locations.
If the product line has been designed with some interchangeable
parts, modest WIP kanbans of “bright
stocked” parts can be maintained at the end of feeder shops.
Examples of such products abound: inkjet printers, Q-tips, store
brand aspirin. They are
typically manufactured in a discrete or repetitive environment. “Specialty”
products.
Specialty products display inelastic
pricing and, while not insensitive to competitor’s prices, are much less
so than commodity products.
Margins in such products should
be higher than those of commodity products. In
the customers’ value chain, these products are usually unique enough to
forbear some supply chain inefficiency but reliable fill rates and lead
times will still be required.
Since specialty products have inherent finished goods risk,
inventory should be maintained as far back in the supply chain as
possible.
These will usually exist in an assemble-to-order environment of one
sort or another.
Some examples are:
laptop computers, specialty chemicals, specialized sporting
equipment. There are four manufacturing environments – make to stock (MTS),
assemble to order (ATO), engineer/make to order (ETO and (MTO).
And there are four basic types of plants to accommodate these
various manufacturing environments – V plants, A plants, T plants, I
plants. Recognizing the
issues inherent in each of these types of plants and how those issues
affect the manufacturing middle of the supply chain can make or break the
velocity/flexibility/waste efficient supply chain we are trying to create. “V” plants. Many
end items with a small number of raw materials characterize V plants and
all end items are manufactured using the same basic processes: hence the
name -“V” plant. These
plants and processes often utilize specialized capital-intensive equipment
to manufacture commodity type products usually in an ATO/MTS environment.
The most notable characteristic of V plants is that of a process
dominated by “divergences” as the product moves through the stages of
manufacture. Divergence means
that the relatively few raw materials diverge into a greater number
of intermediate items and those intermediate items diverge into
still more items and so on until final process or assembly. Facilitating flow in such plants is focused on creating cells in the
final process/assembly areas and managing queues in the homogenous process
centers. The problem is that
queues will accumulate in front of bottleneck centers and the bottleneck
will shift as mix changes cause divergence imbalance.
So, if we do two level scheduling – a final assembly schedule and
a homogenous process master schedule at the last divergence point before
the final process – we then have to manage the process bottleneck
centers almost perfectly and make the assembly centers very flexible.
An “Advanced Planning & Scheduling” system that will
effectively manage the queues accomplishes the former and set up reduction
accomplishes the latter. To illustrate, imagine a videotape cassette plant in which there are make
to stock and assemble to order end items.
Tape is made in an extremely complex process and then is slit to
width and cut to length before assembly into a wide number of cassette
cartridges. To get the
velocity demanded in this commodity type business, tape has to be
scheduled to a small buffer of roll stock using an APS system to schedule
materials and capacity simultaneously without “waste” of the capacity. The slit and cut tape then feeds an automated cassette
assembly operation that requires rapid breakdown and set up to assemble to
customer order and to a minimal finished goods inventory. “A” plants. Few
end items and many raw material and parts items in an ETO/MTO environment
are the main characteristics of an A plant.
Here, the raw materials are often commodities, manufactured parts
are unique to each end item and are manufactured in general purpose
process centers, and the routings for these parts are dissimilar.
Unlike the V plant, the flow of materials and parts “converge”
as they approach final assembly. Convergence
means that fabricated parts converge into a subassembly, which, in turn,
converges into another subassembly and so on until final assembly.
The flow and supply chain issue in A plants is one of resource
utilization and capacity planning in the general purpose
work centers. For materials
to flow smoothly, it is vitally important that these centers not be
overused by trying to amortize often-lengthy setups. Otherwise parts will
move from center to center in bursts causing a center to be overloaded one
day and underutilized the next with consequent negative effects on final
assembly due date performance. Balancing flow in an A plant, therefore, is dependent upon reducing set
up time in the process centers and shrinking intermediate parts lot sizes.
In addition, the bottleneck center(s) will have to have buffer
stocks of the common parts in front of the center(s) to allow the center
flexibility to produce non-common parts when needed.
Forecasting and master scheduling must be done at a very early
convergence point in the process, maybe even at the raw materials level.
Consider for example, a metal buildings plant; a custom engineering
intensive business in which lead time performance is critical.
Many kinds of raw steel are fabricated into different building
components in cutting, general machining, welding centers and then are
“assembled” to order on a flatbed for shipment to a customer.
Successful supplier management to receive steel timely and in small lots
is dependent upon master scheduling at the first level in the “common”
bills of material and at the raw steel level and letting MRP plan the
inbound steel shipments. The
bottleneck centers, usually welding, need buffer stocks of often- used
joists and beams to free them to produce custom components when needed.
Last but not least, set up reduction in all the centers will permit
the small lots that preclude wave like materials flow. With all these in place, buildings can be final assembly
scheduled according to the lead time and the middle nodes of the supply
chain guarantee that goods will flow through it without impediment. “T” plants. “T”
plants are characterized by a large number of end items made from a
relatively few common parts. These
plants are similar to “A” plants except that the process is dominated
by divergences almost all occurring at or near the final assembly point.
Such plants are usually ATO or MTS plants in which the catalog of
finished products is so diverse that carrying much finished stock is a
risk. What inventories there
are must be in the common parts that can be configured into multitudinous
end items. Facilitating flow in a “T” plant is almost entirely scheduling and
schedule integrity dependent. With
a large number of common parts being final assembled into many end items
in small lots and many shop orders, the availability of parts at final
assembly is crucial. When
parts are in short supply, those that are committed to pre-existing shop
orders may be “appropriated” for another order considered more
important by it’s foreman. Such
parts stealing impedes flow by introducing the chaos of missed final
assembly order due dates. To optimize flow, scheduling of end items to customer order
in ATO environments or to small stock buffers in MTS shops and pull system
“scheduling” of the common parts to time buffers in flow/JIT fashion
is the path to follow. Where
bottleneck centers are extensive among the common parts fabrication
centers, an APS would be the preferred approach.
Which ever is chosen, maintaining the time buffers is the
overriding manufacturing management discipline to be enforced in a “T”
plant. A good example of an “T” plant is a wiring devices plant – an MTS
environment - in which sockets, receptacles, connecters are final
assembled from numerous stamped/tapped metal parts, plastic molded items,
purchased parts into thousands of different end items.
A plant such as this requires that parts from fabrication shops be
available to assemble when stocks of finished goods diminish to the point
where customer service may be jeopardized.
The constant danger is that inventories of these parts will grow
and become a working capital burden on the company. The tendency of these parts to grow in such a business is
directly related to the complicated and often long machine setups in the
fabrication shops and the natural desire to amortize the setup.
The key to optimizing flow (without large, financially burdensome
inventory) is to insure a constant stream of fabricated parts in small
quantities in a controlled environment to flexible flow assembly lines.
The critical needs are for setup reduction to allow small lot
production and possibly for controlled storerooms to protect parts from
misappropriation. The
scheduling options are threefold in this type of plant: use a pull system
to schedule fabricated parts to time buffers and master schedule end
items; use MRP to schedule fabricated parts and final assembly schedule
end items to order; use a pull system to schedule fabricated parts and end
items to time and stock buffers respectively.
“I” plants. Make
to stock with many components and either few or many end items
characterize “I” plants. Typically,
the process consists of many functional departments making common parts
and subassemblies. The parts
and subassemblies “converge” throughout and especially at or near the
final assembly point. The
stocked finished goods strategy often is to have product deployed in
multiple locations. These plants have issues similar to those of V and T
plants where there are many common components made in large functional
work centers resulting in queues in front of bottleneck centers and the
temptation to “appropriate” parts.
The way an “I” plant is scheduled is one of the keys to creating a
smooth flow; the other is close tolerance finished goods inventory
management. Since these are
usually MTS plants and most MTS businesses incur inventory risk when they
carry any significant amount of finished goods, the natural desire is to
deploy as small quantities of stock as possible.
Although there are other approaches, a good scheduling combination
is to master schedule end items using a “close in” forecast or VMI and
use a pull system to flow common parts to final assembly. The “I” plant is often found in the consumer goods industries -
electronic gadgets, sporting goods, tools, toys, home computing
accessories – in which lead times are short and customers will fill
shelves with another product if yours isn’t available.
A jigsaw puzzle plant is a good example.
“Parts” are imprinted and die cut in common process shops in
numerous varieties and meet up with a significant variety of boxes in
which to be packed at the final assembly line.
These are toys and are subject to changing tastes from season to
season so carrying inventory presents risk.
Once the decision as to the product mix for the season has been
made, a “campaign” can be launched to build some stock for the initial
periods of the season but then the process centers that imprint and die
cut have to be managed to keep a flow of small lots moving to the flexible
assembly lines. In an operation such as this, quick changeover and an APS in
the process shops will keep inventory risk to a minimum. THE
“HEART” OF THE SUPPLY CHAIN
All the emphasis on the “extended enterprise supply chain” is
appropriate to successful competition in the modern world economy.
Making suppliers adjuncts of their customer’s factories was the
vision of the JIT movement and was clumsily done when it was done at all.
That vision is currently becoming reality with new and better
attitudes about supplier management and relationships.
Now there is software to enable implementation of the supply chain
management paradigm from beginning to end.
Certainly the new ERP packages and, the bolt on APS software and
extended enterprise SCM software provide all the systemic tools we need
for success in supply chain management. The heart of the supply chain is it’s center, the shop floor, and for
goods to flow in a seamless fashion from raw material supplier to
customer, they have to get though manufacturing in a smooth flow.
A manufacturing operation that still processes goods in batch mode,
however disguised, will be the impediment to successful supply
chain management. Identifying
the supply chain needs of the market in relation to the company’s
manufacturing environment and then executing a scheduling and operations
strategy to meet the needs of both (supply chain/manufacturing strategy
table) will transform even the most stubborn batch operation into the key
contributor to a smooth and seamless supply chain.
Related
Services:
Back to Top Back to Home Back to Articles ![]()
The Remington Group, LLC 475 Wall Street Princeton, New Jersey 08540 (609) 497-6400 |
|
|
|
|
Copyright © 2000 The Remington Group, LLC |
|
|
|